Material Review Board Guide: Link MRB Dispositions to Design

Material Review Board Guide: Link MRB Dispositions to Design
Contents
  1. Step 1: Define what your MRB is and what it decides
  2. Step 2: Write the nonconformance so engineering can judge it
  3. Step 3: Pull the requirement, design intent and change history behind the feature
  4. Step 4: Choose the disposition: use as is, rework, repair, scrap or return to supplier
  5. Step 5: Get engineering sign-off and any customer, contract or regulatory approval
  6. Step 6: Record the disposition rationale so it survives audits and handoffs
  7. Step 7: Feed repeat dispositions back into a design change and re-check affected requirements
  8. What to do next: MRB troubleshooting and where Tandem fits alongside your QMS
  9. Judge every disposition against the design, then change the design

A material review board (MRB) is a cross-functional group, usually quality and engineering, that decides what happens to product that does not meet its requirements: use as is, rework, repair, scrap or return to supplier. This guide shows you how to run one so every disposition is judged against the requirement, the design intent and the CAD change history behind the part. Done right, repeat dispositions turn into a design change instead of a pile of closed reports.

You need three things before you start: a nonconformance procedure your quality system already defines, a named group with authority to disposition, and access to the drawing, requirement and revision history for the part in question. Your QMS runs the nonconformance workflow. What follows is how to make the board's judgment better and its output durable.

Step 1: Define what your MRB is and what it decides

MRB stands for material review board. The acronym is the same in production, in engineering and in documentation, though the usage differs slightly in each.

What is MRB in production? It is the point where a part, assembly or lot that failed inspection stops moving and gets a decision. Nothing ships, nothing gets reworked on a hunch, and nothing is quietly scrapped. The board decides.

What does MRB mean in engineering and quality? It is a company-defined, authorized review process. The term MRB is not an AS9100 term. Your own procedures, customer contracts and any delegated authority define what your board can and cannot decide. Write that authority down.

What is MRB in documentation? Two records get called by this name. The MRB document is the record of one disposition: the nonconformance, the evidence, the decision, the rationale and the signatures. An MRR, or material review report, is the same idea under another name at many companies. Pick one term, define it in your procedure and use it everywhere.

Define four things in writing before the first meeting:

  • Membership. Quality and engineering at minimum, plus manufacturing, and supplier quality when the part is purchased.

  • Authority. Which dispositions the board can approve alone and which need a customer, contract or regulatory approval.

  • Triggers. What sends a nonconformance to the board instead of being corrected at the bench.

  • Output. What record the board must produce, and who owns the design follow-up.

Step 2: Write the nonconformance so engineering can judge it

A nonconformance is judgeable when it states what was built, what the drawing and requirement say, and the gap between them, in that order. Most weak MRB meetings come from reports that say "out of tolerance" and nothing else.

For every item, capture:

  • The part and revision. Part number, drawing revision and the model revision it was built against. A part built to a superseded revision is a different problem from one built to the current revision.

  • The feature. The specific dimension, callout or note that was missed, referenced to the drawing.

  • As built vs. as required. The measured value next to the toleranced value, with the measurement method.

  • The requirement behind it. Not just the drawing callout, but the requirement the callout serves, if you can name it.

  • Quantity and location. Lot, serial numbers, and where the affected product is now, including anything already shipped or installed.

Write the gap in one sentence a design engineer can read cold: "Bore diameter measures 0.004 in over the upper limit on 6 of 40 units, Rev C drawing, feature called out for bearing press fit." If the author cannot say what the feature does, that is the first thing the board needs to find out.

Step 3: Pull the requirement, design intent and change history behind the feature

Before anyone proposes a disposition, the board needs to know why the feature is dimensioned the way it is. A tolerance is the visible end of a decision, and the decision is what you are being asked to override or uphold.

For the nonconforming feature, pull:

  • The requirement. The parent requirement the feature traces to, and the verification that was planned for it.

  • The design intent. What the designer was protecting: a fit, a seal, a load path, a thermal margin, an assembly clearance.

  • The CAD change history. When the feature last changed, what changed, and what else moved with it. A tolerance tightened three revisions ago after a field failure reads very differently from one nobody ever questioned.

  • Design review history. Comments from earlier reviews on this feature, including manufacturability feedback.

Most teams skip this step, because the information lives in a drawing, a requirements tool, a CAD feature tree and a few Slack threads. Tandem is the context layer that keeps that record in one place: requirements with their redlined change history, system architecture, CAD changes grouped into described design goals, and design review annotations tied to geometry and requirements. Pulling the context behind a feature becomes a lookup instead of an archaeology project. Your QMS runs the report and the workflow. Tandem holds the record the board judges against.

For related practice on keeping tolerance rationale attached to the model, see Tolerance Stack-Up Documentation: Keep Decisions With CAD.

Step 4: Choose the disposition: use as is, rework, repair, scrap or return to supplier

Pick the disposition by asking what the evidence from Step 3 says the feature must still do, then match the cheapest option that preserves it. There are five standard outcomes.

Disposition What it means What must be true
Use as is Accept the item with the deviation unchanged Documented technical justification that the requirement is still met; any customer or other required approval obtained first
Rework Correct the nonconformity so the item meets the original requirement Work is documented and conformity is verified before release
Repair Make the item usable without restoring full conformity to the original requirement Engineering and MRB approval, plus customer or contract approval where required, before the repair is carried out
Scrap Prevent the item from being used or shipped as conforming product Item is identified, segregated and its disposition is documented
Return to supplier Send supplier-originated nonconforming material back Handled through your purchasing and supplier-control process

Two habits keep this honest. First, never let "use as is" stand on cost or schedule alone. The justification has to be technical: this deviation does not affect the requirement, and here is why. Second, treat repair as a different decision from rework. Rework restores conformance. Repair does not, which is why it usually carries more approval.

Step 5: Get engineering sign-off and any customer, contract or regulatory approval

Engineering provides the technical assessment for use as is and repair, but engineering approval alone does not override customer, contract, regulatory or delegated-authority requirements. Check the second list every time.

Before the disposition is final, confirm:

  1. Engineering has signed the technical justification, not just the disposition box. The person signing should be able to state which requirement and which design intent the justification rests on.

  2. Customer or contract approval has been obtained where required. In government-contract work, for example, the contractor's MRB may recommend use as is or repair while the customer's approval is also required.

  3. Regulatory constraints have been checked. In medical device work, a concession is permitted only when it is justified, approved and consistent with applicable regulatory requirements (ISO 13485:2016, clause 8.3).

  4. The approver's identity is recorded. Records should show who authorized the concession, not only that one was granted.

If the approval is outstanding, the product stays quarantined. A disposition that is "approved pending customer response" is not approved.

Step 6: Record the disposition rationale so it survives audits and handoffs

A disposition record survives an audit when a stranger can read it two years later and understand why the board decided what it decided. The decision alone is not enough. The reasoning is what gets questioned.

You must control nonconforming outputs and retain documented information about the nonconformity and the actions taken, including concessions obtained. ISO 13485:2016, clause 8.3, asks for a documented procedure defining responsibilities and controls for evaluating and dispositioning nonconforming product, and records that include the rationale for any concession and who authorized it.

Your MRB document should carry:

  • The nonconformance as written in Step 2, with part, revision and feature.

  • The requirement and design intent the board relied on, with a reference to where each lives.

  • The evidence considered: measurements, analysis, test data, prior design review comments.

  • The disposition, the technical rationale, and any conditions attached.

  • Approvals: engineering, customer, contract, regulatory, with names and dates.

The weak point is almost always the references. A rationale that says "per design intent" and points to nothing rots quickly. When requirements, design rationale and review history sit in one connected record, the MRB document can point at the live source instead of pasting a screenshot. For the audit side of this, see AS9100 Design Change Records for Aerospace Quality Engineers.

Step 7: Feed repeat dispositions back into a design change and re-check affected requirements

When the same feature keeps landing in front of the board, the drawing is the problem, not the parts. Treat repeat dispositions as a signal and send them back to design.

Track three patterns:

  • Repeated use as is on one feature. If the board keeps accepting the same deviation, the tolerance is tighter than the requirement needs. Loosen it through a design change and stop spending board time on it.

  • Repeated rework or scrap on one feature. The feature may be hard to make as drawn. Bring manufacturing feedback to a design review on the geometry itself.

  • Repeated supplier returns on one part. The drawing may be ambiguous, or the requirement may not be reaching the supplier.

When the pattern points to a design change, make it a real change with its own impact check. In Tandem, a design change shows a before and after 3D CAD diff with a plain-language summary and the affected requirements and annotations. ECOs, ECNs and documentation can be generated from captured CAD changes in your own templates. After the change, re-check the requirements the feature traces to and confirm their verification still holds. If you run a PLM, Tandem can run alongside it and push and pull data to and from it.

For the change side of this loop, see ECOs From CAD Changes for Medical Device Manufacturing Engineers.

What to do next: MRB troubleshooting and where Tandem fits alongside your QMS

If your MRB is slow or inconsistent, check these first:

  • Meetings spent reconstructing why a feature exists. The context is not retrievable. Fix Step 3.

  • Dispositions that get reopened in audits. The rationale is thin or points at nothing. Fix Step 6.

  • The same part shows up every month. Nobody owns the design follow-up. Fix Step 7.

  • Use as is feels like a default. Require a written technical justification tied to a named requirement.

  • Approvals arrive after the product moves. Add a hold until Step 5 is complete.

Keep your QMS as the place where nonconformance reports and MRB workflow run. Tandem sits beside it as the record the board judges against: requirements, design intent, system architecture, CAD change history and design reviews, plus the design change that follows a repeat disposition.

Judge every disposition against the design, then change the design

A material review board is only as good as the context in front of it. Make the nonconformance judgeable, pull the requirement and change history before anyone votes, record the rationale so it survives an audit, and send repeat dispositions back as design changes. To see how Tandem keeps the requirement, design intent and CAD history behind each feature ready for your next MRB, book a demo.

Visit Tandem

Tandem is the AI platform for hardware engineering. It connects requirements, system architecture, CAD design changes, design reviews, PDM and validation evidence in one system, so design intent survives every review, change and handoff. It works inside SolidWorks, Onshape, CATIA, NX and Fusion and alongside PLM, Jira, Slack and Teams, for hardware teams building complex products from prototype through production.

Get started

Sources

Frequently asked questions

What does the acronym MRB stand for?

MRB stands for material review board. It is a cross-functional group, typically quality and engineering, that evaluates nonconforming product and decides its disposition: use as is, rework, repair, scrap or return to supplier. The board's authority is defined by your own procedures, customer contracts and any delegated authority, not by AS9100 itself.

What is MRB in production?

In production, the MRB is the review point where a nonconforming part, assembly or lot is held and given a documented disposition before it moves on. Nothing is reworked, shipped or scrapped on a hunch. Tandem does not run this workflow; it holds the requirements, design intent and CAD history the board judges against.

What does MRB mean in documentation, and what is an MRR?

In documentation, an MRB document is the record of one disposition: the nonconformance, evidence, decision, technical rationale and approvals. MRR usually stands for material review report, and many companies use it for the same record. Pick one term, define it in your procedure and keep the rationale linked to the requirement and design intent.

Who can approve a use-as-is or repair disposition?

Engineering provides the technical assessment, but engineering approval alone does not override customer, contract, regulatory or delegated-authority requirements. Use as is needs documented technical justification, and repair needs engineering and MRB approval plus customer or contract approval where required, before the work is done.

How do repeat MRB dispositions lead to a design change?

Repeated use-as-is dispositions on one feature suggest the tolerance is tighter than the requirement needs, while repeated rework or scrap suggests it is hard to make as drawn. Send the pattern to design as a change. In Tandem, the change shows a before and after CAD diff and the affected requirements.

Related reading

Written by

Tandem

Tandem is the AI platform for hardware engineering. It connects requirements, system architecture, CAD design changes, design reviews, PDM and validation evidence in one system, so design intent survives every review, change and handoff. It works inside SolidWorks, Onshape, CATIA, NX and Fusion and alongside PLM, Jira, Slack and Teams, for hardware teams building complex products from prototype through production.